The articles here are in chronological order. For the latest, go to the bottom.
Bear Valley Water District Told It Must Stop Effluent Spills; Bear Valley Limited To 4 New Single Family Homes For The Year 2000
At a hearing in Sacramento on January
27, 2000, the Central Valley Regional Water Quality Control Board imposed a Cease and
Desist Order on the Bear Valley Water District, operator of the Bear Valley/Lake Alpine
sewer system; the Board imposed a limit of 4 new single family sewer hookups for calendar
year 2000.
This was a response to several years of effluent spills from a
storage reservoir in the meadow south of Highway 4. The spills were caused by snowmelt in
the uncovered reservoir, diluting the primary treated effluent stored through the winter
until Bear Valley Water District can get rid of it in the summer by spraying it on the
hillside next to the reservoir.
The primary treatment plant only operates at 20% of its capacity, but
the reservoir is too small to hold the effluent plus all the snow that lands on it.
The Regional Board made it clear that they would not tolerate a
continuation of a 5 year pattern of repeated violations by the Bear Valley Water District.
Downstream water users like Stockton East Water District have complained repeatedly about
the spills which end up in the Stanislaus River. Although the effluent is highly diluted
and yields readings comparable to mountain stream water, it is not tested for pathogens
which might be present.
The Regional Board has imposed a tough schedule with several incremental
deadlines for Bear Valley Water District to meet. The theme of the deadlines is
identifying a solution to the overflows, identifying a funding source for the fix, and
building the solution, whatever it is. The Regional Board suspended $25,000 of a $30,000
fine, with the understanding that the $25,000 would be applied to an engineering study to
identify the fix.
The Water District contracted with Boyle Engineering of Sacramento to
do the study and guide the Water District through the Region's requirements. At the
District's Feb. 21 meeting, John Burris of Boyle presented his first report and discussed
alternative solutions. He said the easiest and cheapest solution would be to use more
spray field in the summer to draw down the reservoir to a lower level. The Water District
has been negotiating casually with the U. S. Forest Service for several years to buy 200
acres for this purpose, with no result. Now the negotiations are getting more serious as
the District faces the Region's deadlines. It's hard to tell whether the Forest Service
will sell the land after their long and grueling decision process, and it's unknown so far
whether such a transaction would happen soon enough to suit the Region.
Of the private landowners around the reservoir, Bruce Orvis, Jr. is
already taking as much of the effluent as he can. TBH Partners, owners of the meadow, have
said that they will only consider taking effluent if it is safe for human contact, which
means tertiary treatment.
Burris discussed tertiary treatment as an option. It would mean
building a new treatment plant and getting a NPDES permit to spill. Tertiary treatment is
the standard used for effluent that is to be applied where human contact is possible, like
golf courses. It is more expensive to build and operate a tertiary plant than Bear
Valley's present primary treatment system. The good news is that, if you treat to tertiary
standard, you MAY be allowed to spill occasionally. There's no guarantee, however,
that the NPDES permit would be granted.
As to funding, the Water District Board has not made a final
determination, but they are leaning toward a mechanism called an installment sale
agreement. This would allow a rate increase to cover the cost, and it might not require an
election. The Board is still investigating this but it appears that, after public notice
and a public hearing, the Board can levy the increase unless 51% of the ratepayers file a
written protest. The District used bonds in the past but that was before the Forest
Service properties at Lake Alpine and the downhill ski area were allowed into the District
and onto the sewer system. Federal agencies are exempt from bonds but not from
assessments, so using a bond would mean that USFS properties, which contribute 26% of the
effluent in the system, would not pay; clearly an unfair situation for the private
property owners in Bear Valley who would be stuck with the Forest Service's share of the
bill.
An assessment would require an election by the property owners in the
Water District. It would likely be structured like the recent election on the fire
assessment, in that votes would be weighted by the assessed value of each parcel.
How much will this cost? The cheapest we would get away with would be a
land purchase from the Forest Service. The engineer says we may not need 200 acres, the
amount the Water District has been negotiating for; but if it is 200 acres, the price may
be around $1,000 an acre, or a total of $200,000. There would be additional expense for
pipe and the operation of the new spray field.
The most expensive is a tertiary treatment plant. As an example,
Calaveras County Water District just built such a plant for 1200 hookups for $1.6 million.
BV Water District has roughly the same flow to process as CCWD did. But the good news is
that we may be able to retrofit our existing plant with tertiary filters. As of this
writing (3-21-00), the Water District Board thinks we will be able to solve our problem
for less than $1 million, and perhaps for less than $500,000.
The absolute worst case for cost would be building a tertiary treatment
plant and NOT getting a NPDES permit to discharge. That would mean we would have to secure
more spray field, and we might have to expand the reservoir too. No one has tossed out a
cost for expansion of the reservoir.
So the ballpark for cost could be anywhere from $250,000 to $1 million.
How big an assessment would be needed? In very rough terms, a $100 per parcel assessment
or rate increase for 20 years raises $1 million.
Bill Voreyer, manager of the Water District, points out that Bear
Valley sewer customers have had some of the lowest rates in the Sierras for comparable
systems. It appears that those days are coming to an end.
The County Building Department and the Water District are trying to
figure out how to handle the 4 permits we will be allowed. Understandably, neither wants
to be the bad guy in the position of making the final determination on which 4 building
permits/sewer hookups get authorized this year. As of this writing (3-21-00), they are
considering a system whereby the County lets anyone build, with a building permit, but
only 4 people get to hook up to the sewer and thus actually use their new house. And the
Water District has to decide which 4 people get to hook up. So some people might choose to
build, gambling that either they will get a permit, or the restrictions will be lifted
soon.
It all depends on the Regional Board and how they view the Water
District's efforts. The Region could lift all restrictions before we build anything if
they feel that we have our act together and are making speedy progress.
If you would like more information, call the Water District at
209-753-2112. Water District meetings are held on the 3rd Monday of each month at 1 pm in
the Water District Building between the library and the school. The meetings are open to
the public.
Eric Jung June 2000
Update: September 2000: no assessment, rates go up, cost of tertiary lower than at first thought
There's no need for an assessment in the
near future to solve the sewer problem. That's because we now know that we can build a
tertiary plant for less than was originally thought, perhaps $350,000. The Water District
Board raised the annual user fees at its August 21 meeting; a single family home now will
pay $432 a year, up from $288. The fee for a new hookup was also raised from $2,450 to
$4,500.
The increased annual user fees will pay for the tertiary plant for
current users. The fees for new hookups will pay for expansions of the plant, which will
be designed in modular fashion.
The District continues to pursue an NPDES permit, more acreage from the
Forest Service for spraying, the use of private land for irrigation disposal of effluent,
and the possibility of a pipeline to the ski area for disposal of effluent there.
At the August 21 Water District Board meeting, Chairman Dave Ritchie
said construction of the tertiary plant would probably start in spring of 2001. There's no
way to tell whether that would be enough progress for the Regional Board to lift the
hookup restrictions. A waiting list is developing for hookup permits.
So far the moratorium hasn't killed off optimism about Bear Valley's
future. Over 30 lots were sold in Bear Valley in the summer of 2000.
EJ
Update: June 2001: Water District misses on first try for NPDES permit, but still optimistic for July
At its June 14 meeting, the Regional Water Quality
Control Board rejected the Bear Valley Water District's application for an NPDES discharge
permit by a 3-3 vote, despite state staff's recommendation for approval. The Regional
Board also shelved consideration of lifting the partial building moratorium. Some of the
Regional Board members were uncomfortable with the wording of the permit application which
appeared to allow more total spillage than is actually needed.
State staff will work with the District's staff and contract engineer
(Rich Stowell of Eco-Logic) to reword the application, and the application will be back on
the Regional Board's agenda for consideration on July 27.
Update: August 2001: New Hookup Limit Raised to 10 per year
At its July 27 meeting, the Sacramento Regional Water Quality Control Board raised the limit on new residential hookups from 4 to 10 per year. There was no consideration of an NPDES discharge permit.
Update: February 2002: District Asks State to Lift Restrictions
At its February 18 meeting the Bear Valley Water District Board
voted to ask the state to rescind the Cease and Desist Order which currently limits Bear
Valley to 10 new sewer connections per year. The Board is optimistic about its chances,
thanks to new calculations by their engineering firm, Eco-Logic. Eco-Logic's latest study
show that measures taken since the C & D Order was leviedon Bear Valley appear to
guarantee no further overflows of the effluent reservoir. They calculate that the District
can now survive 6 successive years with 100 year storm events.
The C & D Order was imposed when the reservoir ran out of capacity
and treated effluent was released into Bloods Creek. Since then the District signed a
lease with the Forest Service for the use of 40 more acres for effluent disposal. And,
according to District Manager Bill Voreyer, the District has fine-tuned its evaporation
disposal system to get rid of more effluent. This should allow an increase in capacity
from 100,000 gallons a day to 130,000 gallons a day. Eco-Logic feels that this should
allow buildout of Master Planned projects on the north side of Highway 4 for the
foreseeable future, including homes, condos, and commercial development.
What is left out of the calculations for now is development on the
south (meadow) side of the road. Although the Master Plan includes this area, it isn't in
the Water District. The owners, TBI Partners, would have to request annexation to the
District, which would trigger the need for increased capacity. The District has been
talking with TBI about using the open areas of the meadow for effluent disposal. Chuck
Toeniskoetter of TBI has told the District that they will not accept anything less than
tertiary treated effluent on the meadow. The District has been considering tertiary
treatment as one alternative. But if Eco-Logic is correct, it may not be needed yet. Nor
would the District need an NPDES permit to allow discharge of effluent into Bloods Creek.
Just before the District got the new numbers from Eco-Logic, the Board
surveyed the ratepayers about the alternatives. Predictably, the ratepayers overwhelmingly
supported the least expensive alternative, secondary treatement and an NPDES permit. But
if the State accepts Eco-Logic's numbers, there's less chance of getting the permit. The
State would prefer that the District solve its overflow problem without the permit, and
would be less likely to suuport an application for the permit.
Voreyer hasn't ruled out tertiary treatment in the long run, and says
there's a good chance that the District would go to tertiary in the future. But the
District board will discuss that later, he says. The Board wants to get through the short
term problem before starting on longer term planning.
One reason to go to tertiary treatment would be to protect the aquifer
under the meadow. The State is requiring the District to install 6 monitoring wells in
locations around the meadow to start measuring the effect of years of effluent disposal
there. The aquifer is Bear Valley's emergency water supply, according to town founder
Bruce Orvis, Jr.
Voreyer says part of the problem is the logjam the State created for
itself when it imposed C & D Orders on districts all over the state. He notes that
Bear Valley has a chance to be the first of those districts to get out from under a C
& D Order. But the state staff is so busy, he says, that the District is constantly
"fighting to stay on their radar".
He is pleased, however, with the Eco-Logic report, and optimistic that
the State will buy Eco-Logic's numbers, since Eco-Logic has a good track record with the
state. He says that lifting the C & D Order would allow the District to shift gears
from "satisfying the State to satisfying community needs".
EJ
Update: June 7: C&D Order Lifted
At its June 7, 2002 meeting, the Regional Water Quality Control
Board lifted the Cease and Desist Order by a unanimous vote. This means that the building
restrictions are eliminated. The state staff had recommended the lifting of the C&D
Order, since the Bear Valley Water District has complied with all state requirements since
the imposition of the Order. Even the Stockton East Water District agreed that Bear Valley
has done a good job of addressing its problems so far, and did not oppose the lifting of
the Order. Stockton East opposed the granting of the NPDES permit and has kept an eye on
Bear Valley's sewer situation since they are the downstream recipients of any problems
Bear Valley dumps into the Stanislaus River.
EJ
Update: June 17, 2002: Service Rates Increased
The Bear Valley Water District Board
held a public hearing on the proposed 55% increase in sewer service rates. There weren't
enough protests, written or oral, to trigger an election on the matter, and the Board
passed the increase after the hearing, which was mostly a question and answer session.
Points brought out by the audience questions:
1. The increase has nothing to do with preparing for future development. It is necessary
to comply with state mandated monitoring and planning for the existing sewer system.
Expansion of the system's capacity will be paid for by hookup fees from future builders.
2. Metering sewer outflow is not cost effective. Sewer meters on houses would cost at
least $3,000 per house to install. They would require more staff time to read and to
apportion bills. The extra costs would wipe out the small savings a few users might hope
for, and most people's bills would be even higher.
3. The increase will pay mostly for the upfront costs of the state mandates. It is
possible that the rates would go down in 3 years after the monitoring wells are built and
the new costs are reduced to ongoing operations. But the state is in control through these
mandates, and the Water District Board was careful not to guarantee a future decrease in
rates.
4. Bear Valley is not subsidizing the Forest Service users at Lake Alpine and Bear Valley
Mountain Resort (nor vice versa).
5. The Forest Service is exempt from bonds, so the District can't use a bond to raise the
upfront money because only the Bear Valley users would be paying off the bond.
6. The District can't postpone the increase because the mandated programs must be
implemented immediately this summer, incurring engineering and construction costs.
7. The District has run its reserve down dangerously low, so the reserve can't be used to
cushion the blow of the increase. In fact, the District must build its reserve back up
over the next few years.
The basic rate for a single family equivalent unit went from $36 a
month to $56.
EJ
District running out of capacity, will try again for discharge permit
At its January 2003 meeting, the Bear Valley Water District Board
heard a report from their engineer, Neal Calwell, that they only have capacity for 50 more
hookups. The board tentatively awarded 21 of those hookups to the Pine Tree Village condo
project.
At its February 2003 meeting, the Board voted to ratify the award of 21
hookups to Pine Tree Village. The project must pay for the hookups within 6 months whether
they start construction or not, and they must use them within two years or the Board can
take them back (after refunding the hookup fees). The Board also voted to try again for an
NPDES permit from the state. This discharge permit would allow occasional releases of
treated effluent into Bloods Creek and down into the Stanislaus River. The District just
missed getting a permit in 2000 when a technical error in drafting the application
confused the State Board members, resulting in a tie vote and no permit.
The Board voted to approve $87,000 for Eco-Logic engineering firm to
prepare a new application. Over half of the cost goes to testing samples from the effluent
reservoir and Bloods Creek.
EJ
District Resubmits Application for Discharge Permit
Engineer Neal Calwell told the District Board at their
June 2004 meeting that he has submitted a new NPDES discharge permit application. If the
Regional Water Quality Control Board grants the permit, it would give the District more
capacity headroom. Calwell said the Control Board staff has 30 days to decide whether the
application is technically adequate. If it is, it would be set for a hearing with the
Control Board. Calwell says it may be a few months before a hearing even if there are no
problems with the application.
EJ
District Gets Discharge Permit
At its October 21, 2005 meeting, the Regional Water Quality Control
Board voted unanimously to approve the Bear Valley Water District's application for an
NPDES discharge permit. Most of the permit conditions were no surprise, but there was one
big surprise. When District Board members Dave Ritchie and Brian Neth arrived in
Sacramento for the Regional hearing, state staff told them that their application was
likely to be rejected unless the District agreed to upgrade from secondary to tertiary
treatment. Ritchie and Neth agreed.
The District Board held a special meeting on October 29 to ratify the
permit with its conditions. After a 45 minute discussion, the Board voted 4-1 to approve.
The permit solves Bear Valley's sewer capacity problem for now. The
District must implement tertiary treatment by October 1, 2008. At the District's November
21 meeting, engineer Neal Calwell will bring preliminary cost figures for a modular
tertiary treatment plant, along with the costs of other permit conditions, mostly related
to increased monitoring.
The permit will allow the District to release from the storage
reservoir when there is danger of overfilling. Releases may occur only when the treated
effluent is diluted at least 20 to 1 by snowmelt.
EJ
WATER DISTRICT BOARD PITCHES ASSESSMENT
This article is a summary of what was presented by the BVWD Board. It does not represent an opinion or position taken by BVRI, but rather is intended to further inform the community about what was discussed at the meeting.
At a public workshop on Saturday, December 29, 2007, at the Perry Walther Building, the Bear Valley Water District Board presented a picture of Bear Valley’s sewer problem and their proposed solution.
The problem presented is a history of spills from the reservoir which holds treated effluent during the winter until it can be disposed of in the summer. The solution proposed is a tertiary treatment plant which would raise the effluent to a standard allowing legal discharges into Bloods Creek and ultimately into the Stanislaus River.
District Engineer Neal Colwell of EcoLogic explained that, while the District has had occasional spills for many years, the attitude of the state and downstream water users changed in 1999. When the District had an overflow in 2001, the state fined the District $35,000 and imposed a building moratorium.
The District applied for an NPDES permit which would have made occasional discharges legal under controlled conditions. The Regional Water Quality Control Board turned down the application. The District then leased 40 more acres from the Forest Service to augment the land used for spray disposal of the effluent. EcoLogic estimated that this would solve the problem by allowing the reservoir to be drawn down further every summer. But the estimate was proven wrong in the winter of 2004-5 when heavy snow and a late winter raised the level in the reservoir and delayed the spray disposal. The District had to sandbag the spillway of the reservoir to prevent another discharge.
The District Board has been weighing alternative solutions since the 2001 fine. Plans considered and rejected included roofing the reservoir, raising the height of the reservoir, or buying more land for summer disposal. The Board then decided to try again for the NPDES permit. The Regional Board granted the permit, but with an important proviso: the District would have to raise the treatment standard from secondary to tertiary.
Colwell outlined the estimated cost of building and financing a tertiary plant, $14,702,000. The Board considered financing options. Due to the high median household income levels in Bear Valley, the community will not qualify for competitive grants. The Board considered a loan, and raised hookup fees from about $6,000 to about $15,000. But this would not have brought in enough money up front, since it would have relied on future development which may or may not occur.
The Board settled on an assessment as the fairest mechanism to finance a bond to bring in enough money up front to build the plant. Audience members questioned whether existing ratepayers would be paying more than their fair share to allow future development. Board member Jim Bissell explained that it will cost $10 million to build a plant to serve just the existing users, while adding $2 million more would allow for a plant which could handle full buildout. He noted that the assessment would capture money from all parcels in the District, based on both present and potential future use, so that all users would be paying a fair share. The vote on the assessment would be weighted by each parcel’s present or future use entitlement. That means that the owners of the parcels master planned for future development would have enough voted to pass the assessment by themselves.
There was much discussion of the fact that a lot of the water in the reservoir is not sewage from houses, condos, or businesses. Snow that lands on the reservoir, snowmelt that leaks in from around the reservoir, and water that infiltrates the pipes all add to water in the reservoir. Board members explained the ongoing efforts to reduce infiltration, including smoke testing of pipes and manholes, and plugging leaks where found. Responding to a question about conservation, Board President Dave Ritchie said all new construction is required to use low flow plumbing fixtures.
The cost of roofing the reservoir is estimated at $10 million. Raising the reservoir or putting a wall around the top would be expensive, and adding to the reservoir’s capacity would create the problem of finding more land to dispose of the increased pool. And surrounding landowners have declined to discuss the sale of any more land, either for spray disposal or reservoir expansion.
The Board emphasized the fact that the state is now requiring Bear Valley to implement tertiary treatment, regardless of whether any further building occurs.
The Board will continue to take public input before proceeding with steps leading to an assessment vote. The Board assured the audience that they will appreciate any suggestions for alternative solutions. A no-action solution – maintaining the status quo – doesn’t seem feasible, since it would result in more spills and heavy fines by the state.
More information can be found at www.ecologic-eng.com/project_links.htm; user
name, bvwd, password, tertiary. You may send comments to
BVWD@ecologic.com.
EJ
DISTRICT BOARD GETTING HELP
3-08
The Bear Valley Water District Board is getting advice from outside sources. At its February 18 meeting, the Board approved a contract with Bonneau Dickson, an expert on effluent treatment, to do an 80 hour study of the situation, including an opinion on whether tertiary treatment (and the assessment to pay for it) may be avoidable, as well as an appraisal of the predesign for the proposed treatment plant. At its March 17 meeting, the Board was presented with a preliminary report by Mr. Dickson.
Regarding the need for tertiary treatment, Dickson said that the District might be able to avoid the need for tertiary treatment (and the NPDES discharge permit) if it could find ways to dispose of 25 million more gallons of effluent than it can now. He listed ways this might be accomplished while admitting that he was still studying the situation. None of the fixes he listed was new to the District Board. He noted that land disposal would be the best method, something the state has already ordered the Board to use first, and which the Board has been doing all along. There followed a long discussion of ways to maximize land disposal: getting more land (unwillingness of adjacent landowners, and marginal suitability of adjacent land for disposal); more intensive use of existing disposal fields (mostly already used to maximum absorption capacity, according to District Manager Wilbur Thiede). The Board pointed out that even if it were possible to increase land disposal, that would necessitate increasing the capacity of the reservoir which holds the effluent during the winter until the land disposal happens in summer. Dickson mentioned covering the reservoir (estimated $10 million cost for that) or using aeration and evaporation. Thiede said he can get the reservoir empty, or nearly so, every year. But starting with an empty reservoir doesn't guarantee sufficient storage for a winter which starts early, involves a lot of precipitation, and lasts into June. Dickson asked whether the District could rent treatment facilities for the occasional year when that happens, instead of building a permanent fulltime plant. The problem with that is timing; the problem occurs in the heart of winter, when getting a rented treatment plant out to the meadow facility and setting it up in the snow would be difficult at best. It's never been done, and no one knows whether it's even feasible.
In the end, the best Dickson could offer for now was to ask the District Engineer, Neal Calwell of EcoLogic, to refine the effluent disposal data, while continuing to look for ways to get rid of 25 million more gallons. Dickson will continue to investigate and render a final report later.
If the tertiary plant is unavoidable, as seems to be the case, a Bear Valley homeowner may be able to get the cost down. Bear Valley's John Mallard is a principal of Clean Filtration Technologies, Inc. (CFT), which specializes in prefiltration used in drinking water treatment plants. His company has developed an improved filter system which they used to build and operate a water plant in Honduras. Mallard sent Jerry Breen and Dave Levin to the District Board's February meeting to show the filter. They told the Board that a preliminary look at the predesign for the tertiary plant suggests that they may be able to achieve the required treatment standards for less money in a smaller facility, using their new technology. Mallard came to the March meeting with a proposal for a $50,000 contract in which his company would provide a preliminary plant design and associated documents related to state requirements and approvals.
The Board asked Bonneau Dickson for his opinion. Dickson voiced two concerns. First, while the new filters are approved and in use for drinking water treatment in California and elsewhere, they are not yet state certified for treatment of effluent. Second, he wanted to know how the filter system handles algae, which is normally a bigger problem in effluent treatment than in drinking water. Mallard said he was confident that he could get state approval of his system in time to meet the District's deadlines. His engineer Dave Levin explained how their system handles algae and said it would be no problem. Dickson said he could not recommend the CFT system without state approval. But he also noted that "If you can show it will work, you've got a real moneymaker."
After more technical discussion, the District Board voted 4 to 1 to enter
into the contract with Mallard's CFT. Dissenting Board member Jim Bissell said
he wanted to be conservative, and cited the lack of state approval of CFT's
system. The other Board members felt that, while the $50,000 contract might be a
gamble, the upside is a possible savings of a big part of the potential $14
million tertiary project cost. And the Board felt good about Mallard's
commitment to try to help his community. Board members cited the expressed wish
of the public to explore alternatives to tertiary (hence the contract with
Dickson) as well as ways to reduce the cost of the tertiary project if it turns
out to be unavoidable.
EJ
BOARD CONTRACTS WITH CCWD FOR MANAGEMENT SERVICES
The Bear Valley Water District Board has entered into a contract with neighboring Calaveras County Water District. CCWD will provide management services. The Bear Valley Board had been considering hiring its own District Manager, and decided that a contract with CCWD would give a broader range of services and expertise than hiring a single individual. The contract calls for a minimum of one day a month onsite and one day a month offsite plus attendance at the Bear Valley Board's monthly meeting. Beyond the minimum, CCWD will be available for more time up to a maximum of $60,000 a year. The contract minimum could be as low as $21,000 a year. CCWD operates a number of water and sewer treatment plants in Calaveras County, and will be able to provide support in areas of management, maintenance, finance, plan check, and grant application and administration.
CCWD's Bill Perley reported to the District Board at their August meeting that he had brought up various CCWD staff people to do an initial assessment of the Bear Valley District's operation. He told the Board that they are doing a good job. He also reported that he and his staff are looking over the preliminary plans for a tertiary plant, and their initial review suggests that prefiltration, a significant component of the tertiary process, may not be needed. That could mean a significant savings in plant construction and operation.
Consultant Bonneau Dickson also appears to have saved the District some
tertiary plant costs. His review of the District's situation suggested that the
water balance (the description of effluent quantities handled by the District)
used to estimate the size of the tertiary plant were probably too high and
should be recalculated. The water balance numbers were indeed recalculated, and
the new numbers suggest that the size of tertiary plant needed is smaller than
originally thought. This could save up to a million dollars in plant cost.
EJ 9-11-08
BOARD CLOSING IN ON TERTIARY PLANT DESIGN
The Water District Board appears to be close to selecting a tertiary plant design. At their February 23, 2009 meeting, CCWD's Bill Perley told the Board his concerns about the Mallard/CFT plant design: namely, the prefiltration component may not be necessary, and CFT's equipment may suffer from frequent downtime between peak loads. It may also be necessary to build a roof over CFT's modular plant. CFT says they can build a plant to their design for about $2.6 million. Ancillary costs would bring the total price tag to around $3.3 million. Perley said he and his staff could put together a proposal for a more conventional design that would cost around $4 million. The Board directed Perley to meet with Mallard and have him (and CCWD) bring complete enough specifications to the March 16 meeting to allow the Board to pick between CFT's proposal and CCWD's.
The Board discussed how to pay for the plant. CCWD General Manager Dave Andres told the Board about various state and federal loan and grant programs. The federal economic stimulus package offers interesting possibilities as well. The Board asked Andres to pursue all avenues. An assessment district is still a possibility. Its advantage is that it would allow assessment of undeveloped properties, spreading the costs over a wider base. Its disadvantage is the cost of setting up the assessment. If the costs of the plant are recaptured through the user fees, current users would pay a higher amount up front. As new development comes on line, it would be required to "catch up" through hookup fees, at which time the rates should go down for already existing users.
The Board discussed the District Engineer position, now held by EcoLogic. Perley told the Board that he has gradually taken over some of the duties of the District Engineer. He and Andres assured the Board that they could handle everything now done by EcoLogic, and probably for less money. The Board encouraged Perley to accelerate the transition from EcoLogic to CCWD. Although it was not explicity stated, we can assume that the District will terminate its contract for District Engineer duties with EcoLogic and enter into a new one with CCWD in the near future.
The March 16 meeting may see the District take a big step toward resolving the problems that started in 2000, if they select a tertiary plant design. That will give the District a clearer financial target, and allow the Board to home in on a financing mechanism. It would also make the state happy to know that, after a protracted period of discussions and a deadline extension from the state, the District is ready to move forward.
BOARD PREPARES FOR ELECTION ON RATE INCREASE TO FUND PLANT
At its April 20, 2009 meeting, the District Board voted 3 to 1 to support in concept the plant design from Clean Filtration Technology, based on the successful operation of the pilot plant. Bruce Orvis made the motion. Phil Davis and Dave Ritchie voted in favor. Jim Bissell voted against, saying the motion wasn't specific enough. Brian Neth was absent. The motion was at least partly symbolic, since it doesn't bind the Board to the CFT design. The Board will continue to look for the best (and cheapest) way to build the tertiary plant the state requires. But it's getting late in the game, and the chances of a viable competing design coming forward are getting slim. The CFT design has a $2.6 million price tag. Calaveras County Water District submitted a more conventional design with a $4.1 million price. And the Board has already discarded a design submitted by EcoLogic with a $12 million price. The motion was a vote of confidence for CFT owner and Bear Valley homeowner John Mallard, whose company has put considerable time and effort into solving Bear Valley's sewer treatment problem. As District Board President Dave Ritchie said, "We want to show the public that we're moving forward."
The Board discussed how to pay for the plant. CCWD's Bill Perley has been exploring various alternatives. He told the Board that a USDA loan is available for up to $5 million at 5% for 40 years. F&M Bank has offered a $2.45 million loan which isn't enough, but the Board is still negotiating with them for better terms. Perley has applied for various other funding sources including economic stimulus package money. He noted the possibility that some or all of the funding could come in an outright grant or a no-interest loan. He even mentioned a "negative interest loan", but no one is sure what that means.
Then there's the matter of how to repay a loan. The Board has apparently given up on the lease-purchase option proposed by Mallard, whereby the plant would be financed and built by a consortium of private investors. The problems with that method are that the interest rate would be 8.5 to 9%, and it might need to be paid off with a huge balloon payment in five years. The Board also considered an assessment district, whose main advantage would be that all parcels would be assessed, including parcels as yet undeveloped, thus spreading the cost over a wider base at first. But forming an assessment district is a long and expensive process which would add $600,000 to the costs.
The Board agreed that the simplest and cheapest way to recapture loan costs would be through a simple rate increase on existing users. Future users would be charged a bigger hookup fee to "catch up" with the existing users, which would then lower the rates for those who had already been paying. The rate increase must be approved by the ratepayers through a Proposition 218 election. The District sends out a notice to ratepayers of the proposed increase. Ratepayers then have 45 days to protest. If half the ratepayers plus one protest, the rate increase fails. Protests may be registered by mail, e-mail, or in person. The Board wants to have the 45 day period end at their June 15 meeting, which means they'll have to send out the notices by May 2. The notices will peg the rate increase at the worst case, to allow for contingencies and cost overruns. But the Board assured us that they will try to hold the costs down as much as possible. Under Prop. 218 rules, the District can levy lower rates than stated in the election without going back for another Prop. 218 election. But if costs exceed the estimates, they'd have to go back to the ratepayers for another election, which they'd like to avoid.
A Bear Valley homeowner asked the Board to rethink the rate structure. Currently, there's an added fee if you have more than two bathrooms. The contention was that more bathrooms don't necessarily generate more sewage. Dave Ritchie said he saw a study showing that bigger houses in resort communities have lower occupancy rates. But rate adjustments based on occupancy rates may be a slippery slope. Owners of Lake Alpine cabins have long contended that they should pay lower sewer rates because of use restrictions on their cabins by the Forest Service. The District has no direct method for measuring effluent from homes and condos. Sewer meters would be expensive to install and monitor. Some homes have water meters, but water usage isn't always a direct measure of sewer output. And as Board member Phil Davis told the homeowner, "If your rates go down, mine go up." The Board asked Bill Perley to look at how other resort communities handle fairness and occupancy issues in billing and report back to the Board. If the Board intends to propose changing the billing structure, they will want to include that in the mailing that's about to go out.
Whether there's still time to get the plant built this year will depend on the results of the election and the requirements of whatever funding source is used. Some funding sources will require public bidding, including drawing up bid specs and publishing them. If that happens, it'll be a lot harder to get the plant done this year, even using CFT's modular design. If the District can avoid the public bid process, CFT might still have time to get the plant done before winter, since the plant is assembled offsite and placed on a pad.
What if the election fails? Bill Perley said the state sent a representative of the Water Resources Control Board to a public meeting of another district which was considering a similar Prop. 218 election. The state representative told the audience in effect, you must approve the rate increase and comply with the state requirements. Otherwise the state will step in and take over the construction project and levy the fees on the ratepayers any way it sees fit. So it's probably better to get it done ourselves.
The Board considered a letter of resignation from EcoLogic as District
Engineer. The Board was already heading in the direction of letting EcoLogic go
and seeking a new District Engineer, and CCWD has already assumed many of the
routine duties of that position. The problem with EcoLogic's letter was that
they wanted to make their resignation effective as of last July 8. The District
Board was unwilling to let EcoLogic off the hook for anything that happened
between then and April 20. The Board voted to accept EcoLogic's resignation,
effective April 20, 2009. The Board will seek a new District Engineer, and has
already received applications from several firms.
EJ 4-24-09